KNS Win City Project Schedule
KNS Win City project schedule runs from layout approval in August 2024 to possession on 23 September 2029. In between sit the RERA start in December 2024 and the pre-launch in August 2025. The official launch then followed on 5 November 2026. Layout works then continue in phases up to the proposed completion date of 23 August 2029. This schedule covers all 1,225 plots across 74 acres in Nelamangala, Bengaluru.
This guide maps every milestone and explains what happens in each stage. It also shows you how to plan your own steps around it.
KNS Win City Master Schedule
| Stage | Date | What Happens |
|---|---|---|
| Layout approval | 23 August 2024 | BMRDA sanctions plan no. NPA/LAO/86 and 87/2023-2024 |
| RERA project start | 2 December 2024 | Official start date on the Karnataka RERA record |
| Pre-launch and EOI | 28 August 2025 | Early buyers block plots through an Expression of Interest |
| Official launch | 5 November 2026 | Bookings open for all seven plot sizes |
| Development phase | 2026 to 2029 | Roads, utilities, parks and clubhouse are built in phases |
| Proposed completion | 23 August 2029 | Layout infrastructure finished as per RERA |
| Possession | 23 September 2029 | Plots handed over to buyers |
The project's RERA number, PRM/KA/RERA/1250/307/PR/290825/008039, links these dates to a legal commitment. You can check the record on the Karnataka RERA website at any time.
Stage 1: Approvals (2024)
Every plotted project in the Bengaluru region needs a sanctioned layout before it can sell. KNS Win City received BMRDA approval on 23 August 2024 for its 74-acre Phase III layout.
The approved plan fixes the land use across the township. Plots take 52.09% of the land, roads take 31.23% and parks cover 11.67%. Six civic amenity sites use the remaining 5.01%. With this plan in place, the project moved to RERA, with a start date of 2 December 2024.
Stage 2: Pre-Launch (2025)
The pre-launch opened on 28 August 2025 for buyers who wanted early access. Through the EOI route, you could block a plot with ₹1 Lakh by cheque or online transfer. A post-dated cheque of ₹5 Lakhs went along with the EOI.
This stage helped early buyers secure their choice of plot size and position. It also let the developer gauge demand across the seven plot sizes before the full launch.
Stage 3: Official Launch (November 2026)
KNS Win City launched on 5 November 2026, which opened bookings to every buyer. The full price sheet now shows base rates of ₹5,999 to ₹6,499 per sq.ft. Plots start from ₹65 Lakhs onwards, and a 30 × 40 plot starts at ₹71.98 Lakhs.
After an EOI, plots are allotted from the stock still available. The booking form and part-booking amount follow within 2 days of intimation.
Stage 4: Development Phase (2026 to 2029)
The development phase is the longest part of the schedule. Here, the developer turns raw land into a serviced layout, with infrastructure built phase by phase.
Here is how works in a plotted township of this size move from start to finish:
| Work Package | What It Covers | Stage in the Schedule |
|---|---|---|
| Site preparation | Plot marking, entry and exit points, boundary works | Early stage |
| Road network | 24-metre boulevards and 12-metre internal roads | Early to middle stage |
| Underground services | Water lines, drains and power cables along the roads | Early to middle stage |
| Plot services | Water connection for each plot and EV charging space | Middle stage |
| Green areas | Parks, avenue trees and open spaces | Middle to late stage |
| Clubhouse zone | 1-acre zone with pool, gym, courts and mini theatre | Late stage |
| Security setup | Gated entrance, security cabins, CCTV and video door phone | Late stage |
Roads and services come first because every plot depends on them. Amenities and finishing works then follow as the completion date gets closer.
Stage 5: Completion and Possession (2029)
The proposed completion date on RERA is 23 August 2029. By this point, the layout infrastructure should be ready for handover. Possession then follows on 23 September 2029, leaving one month for final checks and paperwork.
After possession, you can register your plot, get the khata and apply for a building plan. Karnataka charges 5% stamp duty on property above ₹45 Lakhs, plus a 2% registration fee. With cess and surcharge, plan for about 7.6% of the property value.
Your Buyer Action Plan Alongside the Schedule
The project schedule works best when you match your own steps to it. Here is a simple plan you can follow.
| Year | Project Stage | Your Action |
|---|---|---|
| 2026 | Launch | Shortlist plot size, verify RERA, pay EOI and book |
| 2027 | Development | Arrange your plot loan and track quarterly RERA updates |
| 2028 | Development | Visit the site and review road and utility progress |
| Early 2029 | Near completion | Hire an architect and plan your home design |
| Late 2029 | Possession | Take handover, register the plot and apply for approvals |
How RERA Keeps the Schedule on Track
The RERA registration makes the schedule more than a sales promise. The promoter must post a progress update on the Karnataka RERA portal every quarter. These updates show plots booked and the status of internal works.
If handover runs late, Section 18 of the RERA Act lets you claim interest for each delayed month. Under Section 6, any extension needs RERA approval and cannot exceed one year in total.
For a closer look at stage-wise works, refer to the construction status guide for this project.
How Phase III Fits the KNS Samooha Schedule
KNS Win City is the third phase of KNS Samooha, a 165+ acre township with about 2,500 plots. Each phase runs on its own approval, RERA number and handover date. So the Phase III schedule above differs from dates you may see for earlier phases online.
The earlier phases on the same belt also help you judge the schedule in a practical way. During a site visit, you can see how finished roads, parks and boundaries look in a KNS layout. This gives you a fair benchmark for what Phase III should look like by August 2029.
How the Schedule Shapes Your Payments and Loan
Your cash flow should follow the project schedule closely. The EOI and booking amounts fall due at the start, soon after launch. The balance then moves in line with the agreement terms you sign with the developer.
Many buyers fund a plot through a plot loan and later shift to a home construction loan. A plot in a RERA-registered, BMRDA-approved layout makes this process easier with most lenders. Speak to your bank early, so the loan timeline matches the project schedule.
Also keep about 7.6% of the plot value aside for stamp duty and registration at handover. Planning this in 2026 avoids a last-minute rush in 2029.
FAQs
The schedule runs from BMRDA approval on 23 August 2024 to possession on 23 September 2029. It includes the RERA start, pre-launch, launch and a phased development stage.
Karnataka RERA records 2 December 2024 as the project start date. The project is registered under PRM/KA/RERA/1250/307/PR/290825/008039.
The proposed completion date is 23 August 2029, close to three years after launch. Possession follows one month later, on 23 September 2029.
Roads and underground services such as water lines, drains and power cables come first. Parks, the clubhouse and security setup follow later in the schedule.
Under Section 6 of the RERA Act, an extension needs RERA approval. It applies only in limited cases such as force majeure and cannot exceed one year.
Check the quarterly updates on the Karnataka RERA portal using the project's RERA number. Site visits every few months also help you follow progress.